APP
A sub-committee of the National Assembly Standing Committee on Water Resources, reviewing progress on K-IV Greater Karachi Bulk Water Supply project on Thursday, called for expediting the work to ensure timely completion of the project and provision of tap water to residents of Karachi.
The expected completion date of WAPDA works is June 2027 and Karachi Water and Sewerage Corporation, through simultaneous alternate arrangements, will start pumping the additional water in its current supply network till completion of the augmentation project of Sindh government, likely in 2029, the Convenor of the Sub-Committee, MNA Muhammad Idress stated while talking to media along with other legislators after the meeting.
Stressing on provision of every gallon of the allotted water to the residents of the most populated city and economic engine of Pakistan, he said that the committee received briefings and sought further detailed records of the project to probe in matters relating to inordinate delays despite spending millions of rupees and ascertain the causes and the responsible officials. Final findings and recommendations of the Sub-committee will be submitted in a report to the standing committee for further proceeding, he added.
Syed Aminul Haq, said that WAPDA has completed 73% of its assigned works and those appeared to achieve completion by June 2027; however further delay is visible at part of the KWSC. He added that Sindh government officials have assured that people of Karachi will start receiving water from the K-IV project in 2027.
Earlier in the meeting, chaired by the Convenor of the Sub-committee Muhammad Idrees, the project’s implementation status, reasons for delays, design issues, planning and accountability for the slow pace of work were discussed in detail.
Members sought details about the progress made so far and questioned whether anyone had been held responsible for the delays. They termed the project as vital for meeting the growing water requirements of Karachi, noting that both the federal and Sindh governments expressed their commitment to completion of the project that must not be delayed further. Sindh government and KWSC officers briefed the meeting about K-IV project in detail from its conception in 2003, approval, designing, execution, and delays, flaws, inflated costs, independent reviews, redesigning and other relevant matters.
The feasibility was completed in 2007, the PC-I was floated in 2010 and approved by the Executive Committee of the National Economic Council (ECNEC) on July 18, 2014. After completion of detailed design in 2015 and award of the execution contract and commencement of civil works in July 2016 and partial execution, an independent design review identified serious design problems and work halted by the end 2018, the committee was informed.
The federal government took up the matter in 2020 under the Karachi Transformation Plan, involving the Ministry of Water Resources in the process.